Supply, construction, installation, testing and commissioning of 5,780m of new DN375GRP and DN400 PE100 PN20 distribution main, fittings, pits and access chambers.
Supply, construction, and installation of all precast and in cast situ concrete structures, along Warnbro Sound Ave.
The project also involved the upgrading of 3 Pump Stations: Bluestone Parkway Pump Station, Naples Place Pump Station and Swanson way Pump station. All pump stations received new switchboards and electrical slabs, pumps and odour control.