Since 2005, Cape has worked constantly on the Central discharge facility at Mt Keith which has an internal wall perimeter of 15km. These works involve 3 x long-reach excavators ranging from 30T-50T, 20T LGP excavator, LGP Dozers, padfoot rollers and when required Cat 740 ejector trucks.
To date over 9,000,000m3 of material has been excavated, dried, spread and compacted to continually raise the CTSF. Daily inspection reports, water recovery management and all associated drainage works to maximise water recovery to the decant return pond is managed by Cape as part of this contract.