Load & Haul 775,000m3 of material to build the TSF J Stage 1A/1B
Decommissioning of monitoring bores
Re-location of existing tailings and waste stockpiles
Excavation of selected materials from designated borrow areas and stockpiles located within existing waste dumps, placed and spread to the design lines and grades
Preparation of the embankment footprint area for the TSF embankment construction and TSF basin area
Construction of an underdrainage system and decant tower
Construction of a zoned earthfill embankment including the upstream toe drain.
Construction of a containment trench for the tailings delivery and decant return pipelines.