Cape’s T955 Trencher and SPD-150 Padding Machine made light work of a Gas Pipeline Project in the Goldfields.
The Cape Team completed 2.5km of trenching with 600 cubic meters of pipe bedding and backfilling to allow the installation of a 150mm steel gas main at Dacian Gold’s Mt Morgan Mine 20km West of Laverton.
The trenching was completed in 3 days whilst the backfilling was completed in 2 days which was a cost effective and efficient solution for our client.
Another great example of our CapeAbility.