Cape Dunstans delivered specialist horizontal directional drilling (HDD) services for FMG's Iron Bridge Magnetite Project in Western Australia's Pilbara region. The works formed part of a 135km concentrate and water return pipeline system connecting the mine site to Port Hedland and involved the installation of two large-diameter steel pipelines beneath the Turner River.

The project required precision drilling through challenging hard rock formations, with ground conditions becoming increasingly difficult at depth. Cape Dunstans utilised multiple drilling rigs, advanced magnetic guidance technology and specialist engineering support to manage changing ground conditions, maintain drilling accuracy and complete the crossings efficiently.

Project delivery included:

Design and construction of two 499m crossings for DN650 coated steel pipelines, including engineered pullback operations to protect pipeline coating integrity.

Use of ParaTrack magnetic guidance technology to achieve accurate drilling alignment within a 2m x 2m exit window despite challenging terrain and hard rock conditions.

Concurrent drilling operations using multiple HDD rigs, including the installation of a fibre optic cable crossing, to improve construction efficiency and reduce delivery timeframes.