Cape
  • Crushing, Mining Services & Civil Utilities Services
  • About
    • Company Profile
    • Our People
    • Our RIPPA Values
    • Health and Safety
    • Environmental Policy
    • Quality Policy
    • Whistleblower Policy
    • Community Engagement
    • Supply Chain
    • Projects
  • Service
    • Crushing & Screening Services
    • Fibre Optic Communication & Signalling Cable Installation
    • Gas Pipelines Installation
    • Underground Power Cable Laying Installation
    • Tailings Storage Facility (TSF) and Ponds Construction
    • Water Pipeline Installation & Dewatering Services
    • Trencher Hire and Services
  • Careers
  • Announcements
  • Contact Us
Think Safe
Menu
Cape
  • Crushing, Mining Services & Civil Utilities Services
  • About
    • Company Profile
    • Our People
    • Our RIPPA Values
    • Health and Safety
    • Environmental Policy
    • Quality Policy
    • Whistleblower Policy
    • Community Engagement
    • Supply Chain
    • Projects
  • Service
    • Crushing & Screening Services
    • Fibre Optic Communication & Signalling Cable Installation
    • Gas Pipelines Installation
    • Underground Power Cable Laying Installation
    • Tailings Storage Facility (TSF) and Ponds Construction
    • Water Pipeline Installation & Dewatering Services
    • Trencher Hire and Services
  • Careers
  • Announcements
  • Contact Us

Home / Projects / Jimblebar – RGP6

Jimblebar – RGP6

Power Project: BHP Billiton & Theiss (Newman WA)

The project was located approximately 39km east of Newman and involved detailed earthworks, trenching, bedding, and backfilling of underground services as well as the installation of electrical and communications infrastructure. The scope included:

  • 206,000 bcm of detailed earthworks
  • 41km of Raw Water and Portable Water Pipelines
  • 4km Oily Water pipelines
  • 2km of Slurry Pipeline
  • 2.4km of sewerage rising main
  • 2km of gravity sewer
  • 41.5km Electrical & Communications conduit
  • 25.5km HV & LV cable
  • 4 x RMUs
  • 10 x Transformers
  • 360 x cable markers blocks
  • Construction of light pole footings
  • 430 x Traffic Bollards
jimblebar power project

Project Details

Client. BHP / Theiss
Location. Newman WA, Australia
Project Duration. 12 months
No Fields Found.

About Us

  • Company Profile
  • Our People
  • Our RIPPA Values
  • Health and Safety
  • Environmental Policy
  • Quality Policy
  • Whistleblower Policy
  • Community Engagement

Services

  • Crushing & Screening Services
  • Fibre Optic Communication & Signalling Cable Installation
  • Gas Pipelines Installation
  • Underground Power Cable Laying Installation
  • Tailings Storage Facility (TSF) and Ponds Construction
  • Water Pipeline Installation & Dewatering Services
  • Trencher Hire and Services

More Information

Copyright ©2022 Cape.
  • Privacy Policy
  • Sitemap
Website designed and built by Media Engine