Whiteman Edge Estate Gas Pipeline

12 February 2019

Gas Project: ATCO Gas (Henley Brook WA) The scope of work for this project comprised of two parts: the installation and commissioning of a DN160mm SDR11 PE 100 SW AS4130 pipeline from Lord Street to Starflower Place between Gnangara Road and Park Street and the installation and commissioning of a DN110mm SDR17 PE80B/100 S2 AS4130 pipeline from […]

Read More

Tuart Lakes Lifestyle Village

12 February 2019

Gas Project: WestNet Energy (Mandurah WA) Tuart Lakes Lifestyle Village development in Baldivis required a new natural gas supply for domestic use with all required headworks. The gas supply would come from the DN160mm SDR17.6 PE80B gas main at the corner of McDonald Rd and Fifty Rd, Baldivis. A new 2400m long x DN160mm SDR11 […]

Read More

Pinastar Parade Gas Main

12 February 2019

Gas Project: ATCO Gas (Ellenbrook WA) The project consisted of the installation of approximately 2700 metres of DN150mm CL150 HP Steel gas main along Pinaster Parade and Lord Street, Ellenbrook – from the corner of existing HP085 at Pinaster Parade going south to Park Street, Henley Brook. A total of 10 drill shots were expedited of which […]

Read More

Midland PVC Replacement

12 February 2019

Gas Project: ATCO Gas (Midland WA) The Midland PVC Replacement Project involved the replacement of approximately 2850m of main and associated services including all traffic management and reinstatement associated with the works. This project replaced approximately 2230m of 155PVC with DN160mm SDR17 PE and approximately 620m of 100PVC with DN110mm SDR17 PE within Morrison Road […]

Read More

Mandurah Gas Lateral

12 February 2019

Gas Project: ATCO Gas (Mandurah WA) Cape was responsible for the installation of the high pressure gas pipeline which will ultimately connect the Dampier to Bunbury Natural Gas Pipeline with the Rockingham and Mandurah areas in Western Australia. With a rapidly expanding population in the City of Mandurah there was an increased demand on the dwindling gas […]

Read More

Horrie Miller Drive / Tonkin Hwy Gas Mains Realignment

12 February 2019

Gas Project: ATCO Gas (Kewdale WA) The scope of works included: • 597m of open trenching and excavation works • 234m Horizontal Directional Drilling • 65m Horizontal Directional Drilling through brick structure and stumps • 896m of marker post installation and reinstatement works along the pipeline corridor • Hydrotesting and DCVG survey works

Read More

Mt Morgan Gas Pipeline

12 February 2019

Gas Project: Dacian Gold (Laverton WA) The Cape team completed 2.5km of trenching with 600 cubic meters of pipe bedding and backfilling to allow the installation of a 150mm steel gas main at Dacian Gold’s Mt Morgan Mine 20km West of Laverton. The trenching was completed in three days whilst the backfilling was completed in two days, […]

Read More

Yamarnar Gas Pipeline

12 February 2019

Gas Project: NACAP (Gruyere VIC) In 2018, Cape was contracted to supply the skilled operators and trenching equipment to support the construction of the 200km Yamarna Gas pipeline on the Gruyere Gold Project. Trenching equipment utilised: 3 x Vermeer Trencher T955 2 x Vermeer TrencherT1055

Read More

Connell Avenue Reinforcement

12 February 2019

Gas Project: ATCO (Martin WA) This project required a 900m long DN110mm SDR17 PE100 S2 AS4130 gas main to connect the existing medium pressure gas mains along Connell Avenue, Kelmscott. The new gas main connects the existing end of main near Pries Park Road to the existing end of main near 152 Connell Avenue. This reinforcement […]

Read More